PROJECT 2:
WEST FOURTH STREET SAFETY
Project completion expected in November 2026.
Project Scope
The West Fourth Street Safety Project will reconstruct the roadway and introduce new safety and mobility features along the corridor. Planned improvements include:
-
Roadway Reconstruction
-
Complete rebuilding of the roadway for long-term durability and safety
-
-
Intersection Upgrades
-
New roundabouts at Stoker Avenue and Summit Ridge
-
-
Multi-Use Paths
-
South side: continuous path from Vine Street to Stoker Avenue
-
North side: continuous path from Vine Street to McCarran Boulevard
-
-
Lane Reductions
-
Streamlined roadway with fewer lanes from Edwards Way to McCarran Boulevard to improve safety and calm traffic
-
​These improvements will create a safer, more connected corridor for drivers, cyclists, and pedestrians while modernizing West Fourth Street for the future.
Proposed Roundabout at Summit Ridge Drive

Proposed Roundabout at Stoker Ave

Cross Sections - Safety Plan

Project Schedule
Project Award
Awarded to Sierra Nevada Construction
May - August
-
Work occurring intermittently on westbound side of roadway between Summit Ridge and Keystone Ave. Full roadway construction occurring between McCarran Blvd and Summit Ridge. Single-lane traffic and paving expected in July.
Working Hours
-
Normal working hours are Monday – Friday from 7 a.m. to 7 p.m.
Traffic Control

From now until September, traffic through the corridor will be two-way with one lane open in each direction. Flagger assisted three-way stops at Stoker Avenue and Summit Ridge Drive continue as crews construct the two new roundabouts.
One-way traffic between McCarran Boulevard and Summit Ridge Drive is expected to return in September. Advanced notice will be provided to the community.