PROJECT 1:

WEST FOURTH STREET DOWNTOWN

Currently under construction. Project completion expected in June 2026.

Project Scope

The West Fourth Street Downtown Project will enhance safety, accessibility, and the overall streetscape within the corridor.

 

  • Planned improvements include:

    • Pedestrian and Landscaping Enhancements

    • Wider sidewalks for comfort and safety

  • ADA-compliant ramps at key locations

    • Vine Street and Fourth Street Intersection

    • Installation of new traffic signals

    • Direct connections to the RTC Biggest Little Bike Network

    • Access improvements for the McDonald’s, Jack-in-the-Box, and Lincoln Center entrances

  • Corridor Lighting

    • Installation of new Neon Line streetlights from Keystone Avenue to West Street

    • Together, these upgrades will create a safer, more inviting environment for pedestrians, cyclists, and drivers while supporting the ongoing revitalization of the West Fourth Street corridor.

Proposed Lighting Improvements

RTC Fourth Street Boards_36x24_Page_6.jpg

Proposed Vine St Intersection Improvements

RTC Fourth Street Boards_36x24_Page_5.jpg

Project Schedule

Project Award

Awarded to Q&D Construction 

Phase 2: Intersection & Pedestrian Improvements

  • November to Mid December - winter break, Then April to June.

Phase 2: Neon Corridor Lighting Improvements

  • Timeline: Spring 2006

  • Installation of new Neon Line Streetlighting from Keystone Avenue to West Street